u3a

West Lakes

Gosforth Public Hall Refurb: August 2026 Update

Update to Hall Users 18th August 2026                                                   GOSFORTH PUBLIC HALL

                                                                                REGISTERED Charity No. 223951 Date: 18/08/26

 

PUBLIC HALL REFURBISHMENT PROJECT – August Update

 

Dear Gosforth Public Hall User,

Members of the Public Hall Management Committee met with representatives of our builders, Roland Hill, on Tuesday August 18th

 

Phase One Progress 

 

External work

The render is now complete. It needs a minimum of 28 days before the paint can be applied. This is specialist paint that bonds to the render and, if applied when the render is ready, chemically bonds to the render providing guaranteed protection for 15 years. Some of the walls have render that has been on for 4 weeks now but others for less time. As such painting is likely to continue into early September. There is a small amount of roof work to be completed (mainly Ridge) which will be done by the end of August.

 

Internal work

Decoration is well underway with most of the GADS storeroom, Supper Room and upstairs store complete. The heating is now complete and operational. The floors in the Library and old Kitchen have significant areas of concrete / screed failure due to damp. There was no existing damp proof membrane.  The construction was flagstones on earth then concrete / screed on top. These damp floor areas have been dug out and we’ll need to apply screed, a self-levelling latex and then a damp proof membrane before floor coverings can be laid. There is also a new fire alarm system to be installed which will be mid September.

 

Timeline

We hope the Library, new meeting room (which was the old Kitchen), Supper Room and upstairs stores will be handed over to us by end September. Work hasn’t yet started on the Phase 2 extension as priority has been given to completing the Phase One work being funded by Historic England.

 

If you have any questions, comments or concerns please raise them with Jackie or Karen, or via your Hall User Group contact.

 

Many thanks

 

Jackie Atkinson                                                  Karen Russ

Gosforth Parish Council                                    Gosforth Public Hall Management Committee

Jackie.atkinson500@btJnternet.com               Treasurergwi@gmail.com 

GPH Refurb - Picture 1
GPH Refurb - Picture 1
GPH Refurb - Picture 2
GPH Refurb - Picture 2
GPH Refurb - Picture 3
GPH Refurb - Picture 3